September 24, 2024
Coloring of the courts was completed on Monday, September 23; the nets have been put back onto the courts.
September 24, 2024
In September, the Park District will be repairing cracks in Woodridge Park’s tennis, pickleball, and basketball courts and applying fresh paint. While repairs are taking place, the courts will be closed.
Coloring of the courts was completed on Monday, September 23; the nets have been put back onto the courts.
Coloring of the courts started today.
Striping of the courts is expected to begin on September 19.
Patch work on the courts has been completed. Leveling of the court surface is nearing completion.
Coloring and striping are expected to begin the week of September 16.
Construction will begin on September 10 and the courts will be closed.
Construction is expected to begin the week of September 9. During construction, all courts will be closed.