July 26, 2017
Renovation Final Phase
The renovation project is wrapping up in August and will require a number of facility schedule changes from Aug 21 – Sept 5.
July 26, 2017
Renovation of the Recreation Center of Highland Park is a Phase 1 project identified in
the GreenPrint 2024 Master Plan. The project includes relocation of the Group Exercise studio to the lower level, creation of a new training studio for both personal and small group fitness training, reconfiguration the fitness desk and lobby area, and expansion of the fitness floor square footage. The facility will remain open during construction with limited disruption to patrons.
The top priority identified in the Recreation Center of Highland Park annual fitness member survey for the past three years is the need for more space on the fitness floor as well as dedicated space for stretching. You spoke and we listened.
The renovation of the lower level will take place Mar-Apr 2017 and will include…
The renovation of the upper level will take place May-August 2017 and will include…
Dates | Description |
---|---|
October-November 2016 | Design Development |
November-December 2016 | Construction Documents |
January-February 2017 | Bidding & Negotiation |
March-June 2017 | Lower Level Construction |
April-August 2017 | Upper Level Construction |
September 2017 | Estimated Grand Opening |