The new curb around the elementary play area has been poured.
Port Clinton’s 2-5 and 5-12 playgrounds are scheduled for an update in 2024.
The Park District of Highland Park began planning the playground update in 2023. The planning and design process was collaborative, and the Park District is thankful for all the feedback collected throughout the process. Feedback collected from the community was used to guide the final design for Port Clinton’s playground renovation.
Project Details:
- new 2-5 playground
- replacement of panels on 5-12 playground
- new fence behind the 5-12 playground
- new playground loop path system
- replacement of game table in shelter with seating
- new picnic and gathering area
- site furniture replacement
Other Projects Happening at Port Clinton in 2024:
- replacement and reorientation of the basketball court
- removal of the backstop (NE portion of park on Bloom St.)