The Park District is working with the contractor to continue construction throughout the winter and construction will occur weather permitting.
The Park District is working with the contractor to continue construction throughout the winter and construction will occur weather permitting.
The new curb around the elementary play area has been poured.
Installation work of the new playground curb is underway. The curb line has been framed and concrete is being poured.
The tot lot has been demolished, and the site is being prepared for the installation of the new tot lot playground equipment.
The new tot lot playground equipment has been delivered to the site.
Installation of the new play panels on the elementary playground has started.
Construction fencing has been put up, the park will remain closed until construction is complete.
Construction is expected to begin the week of September 9. During construction, the park will be closed.
The design process has been completed for the Port Clinton Playground Renovation Project. Thank you to everyone who provided feedback through the survey, listening sessions and community meeting, to help shape the final design for the project. See the tot lot rendering here, and see the 5-12 playground updates here.
Construction is expected to begin in August and be completed by November.
On Thursday, November 16, the Park District of Highland Park held a community meeting to present the proposed playground updates for Port Clinton Park and collect feedback on playground equipment options for the tot lot.
Updates include:
• new pathway design to improve park circulation
• reorientation of the basketball hoop
• updates to the 5-12 playground (rather than a full replacement of the equipment)
• replacement of the tot lot (2-5) playground.
If you were unable to attend the meeting and would like to learn more about the project and/or provide feedback, please reach out to [email protected]. The planning team will be collecting feedback until Tuesday, December 5.
This past summer many of you participated in a survey to share your feedback on Port Clinton Park. The Park District of Highland Park will host a community meeting on Thursday, November 16, 2023, at Oak Terrace Elementary School to share the proposed playground design and two playground equipment options.
The meeting will start with a brief presentation providing an overview of the feedback collected this summer, the proposed park layouts, and project timeline. The presentation will outline the Park District’s decision to restore the existing 5-12 playground equipment instead of replacing the full structure. After the presentation, participants will have the opportunity to review the tot lot equipment options and share their preferences. Feedback collected will be used to guide the final playground designs.
Meeting Details:
Date: Thursday, November 16, 2023
Time: 6-7pm
Location: Oak Terrace Elementary School, Multi-Purpose Room
See the survey results from the preliminary playground planning survey here.
We will be at Port Clinton Park on Friday, July 7 from 9:30-11:30am to collect your feedback on the playground renovation.
The Park District of Highland Park would like to hear from you!
There will be several opportunities for the community to participate in the design process and the first is the Port Clinton Playground Preliminary Planning survey. Follow this link to share your feedback in this brief survey.
The overall plan below overviews the design of the project components that have been developed through the design process.
The renderings below show the elements of the west side of the project area.
The concept plan below highlights the project area (red outline) and the project components.
The Park District is working with the contractor to continue construction throughout the winter and construction will occur weather permitting.
Grading and framing of the skatepark elements is underway.
Construction of the skate park elements has started.
Fence posts for the multi-use basketball court have been installed.
The concrete and asphalt for the game area have been installed.
Concrete for the game area is being installed and the curb around the bocce court has been completed.
The path along the skate park and wheel-friendly plaza has been paved.
Prep-work to install the bocce court has started.
Installation of the multi-use basketball court has started!
Prep-work for installation of the new wheel-friendly plaza and skate park is underway!
Demolition of the skate park and basketball court has started.
Prep-work for installation of the multi-use basketball court is underway!
Drainage to the rain garden area has been installed and grading work is nearing completion.
Prep-work for the installation of the game area is underway! Grading and excavation work has been completed.
Construction fencing has been installed.
Areas within the construction fence are now closed for construction.
Construction is expected to begin the week of September 16.
During construction, portions of the south end of Sunset Woods Park will be closed. The basketball court, skate park, and adjacent path will be closed in addition to the area between the main entrance and tennis courts. The main entrance and tennis courts will remain open during construction.
Click here to see a map of construction areas.
Thank you again to everyone who has provided feedback throughout the design process.
The project will go out to bid at the end of July and construction will start in September 2024.
Click here to see the plan.
A Community Meeting was held on Thursday, May 2, 2024 to share concept designs and collect feedback.
Thank you to everyone who attended the meeting, the feedback provided will be used to guide the final designs.
View a summary of the feedback received on the preferred concept designs and the preliminary updates here.
Thank you to everyone who attended the Skate Park Design Meeting!
The feedback provided is being used to guide the design process for the skate park and wheel-friendly plaza.
A Skate Park Design Meeting will be held on Monday, April 1, 2024 to collect community feedback to guide the design for the skate park and wheel-friendly plaza.
At this meeting, the community will have the opportunity to work directly with Professional Skateboarders, Cody McEntire and Julia Brueckler at American Ramp Company to re-imagine the skate park and wheel-friendly plaza.
A Community Meeting was held on Wednesday, February 21, 2024 to share information about the project and collect community feedback.
Thank you to everyone who attended the meeting, the feedback provided is being used to guide the design process.
A Neighborhood Stakeholder Meeting will be held on Thursday, February 15, 2024 at 5:00pm at the Sunset Woods Field House with neighbors that live directly adjacent to the park.
At this meeting, the project team will explain the project scope and will facilitate a conversation about cares and concerns as design work begins.
At the November 15 Board Meeting, the Park District Board of Commissioners approved Lamar Johnson Collaborative’s (LJC) proposal for Site Design and Engineering Services for the Sunset Woods Improvements Project.
LJC will be working with the Park District of Highland Park to design and implement the Sunset Woods Improvements Project.
The Park District of Highland Park was awarded $600,000 through the Open Space Lands Acquisition and Development (OSLAD) grant program administered by the Illinois Department of Natural Resources for Improvements to the southern portion of Sunset Woods Park.
The Project scope includes (the letter corresponds with the layout plan below):
The Park District hired Hitchcock Design Group (HDG) to take the concept plan through to implementation.
The layout plan below builds on the approved concept plan and is based on a survey of existing conditions, dimensions, and utilities. The layout plan will be shared with the Park Board at a public meeting on October 4, 2023. HDG will then complete the construction documents for the project to be bid out this fall.
This phase is funded through the OSLAD grant award and Park District capital budget. (Highlighted in the red dotted line in illustration below)
A: Reconfigured parking lot for improved circulation, landscaping, and viewing of the Lake.
D: New concrete sidewalk for easier beach access for pedestrians walking to the beach.
H: New accessible boardwalk along the beach, improving access to the beach and circulation around Park Avenue Boating Facility.
G: Seating along the boardwalk.
This phase is unfunded. These elements will be designed and bid as alternates to Phase 1, and if funding is available, Phase 2 will be implemented. (Highlighted in the black dotted line in illustration below)
A: The fenced boat parking will not be resurfaced as part of this project but has been identified as a future need.
B: Plaza with pergola, tables, and chairs to enhance patron experience as the beach and provide space for gathering and passive use.
Please note: Park Ave construction begins in September. See new parking configurations.
Districtwide planning efforts, including the Park Avenue Site Master Plan, Beach Management Plan, and the Lakefront Master Plan, support the Park Avenue Access Improvement Plan These plans were enhanced by engagement with the community and patrons of the Park Avenue Boating Facility.
The Park District is working with the contractor to continue construction throughout the winter and construction will occur weather permitting.
New plants have been installed in the beds.
The parking lot improvements have been completed.
New asphalt has been installed and the lot has been striped.
Prep work to install the asphalt parking lot is underway
Concrete curbs, sidewalks, and the overlook have been completed.
Installation of the concrete walk has started
Framing of the curb and walkway is underway.
Demolition of the parking lot is underway.
The construction fence has been installed.
Construction is expected to begin the week of September 30. Construction fencing on site will go up and excavation work will begin.
Construction is now expected to begin the week of September 9. Construction fencing will go up that week.
Construction is expected to begin September 3.
The Park District is working with the contractor to continue construction throughout the winter and construction will occur weather permitting.
Progress has been made on the elementary tower installation.
The new drinking fountain has been installed.
The curb around the tot lot play area has been installed.
Installation of the elementary play area tower has started.
Most of the tot lot play equipment has been installed and installation of the concrete curb around the play areas has started.
Installation of the playground equipment has started!
The site has been prepared for installation of the new playground equipment.
Installation of the new playground equipment is expected to begin today!
The North backstop has been painted and both fields have been restored to grass.
The new playground equipment has been delivered
Painting of the Old Elm Park shelter has been completed.
Demolition of the playground has been completed.
Restoration of the ballfields to grass is nearing completion.
Installation of topsoil in the ballfields is nearing completion.
Clay removal at the ballfields is nearing completion.
Installation of topsoil and seed is expected to begin on Monday 9/16.
Construction fencing has been put up, the playground will remain closed until construction is complete.
During construction, the playground area will be closed. Restoration work on the ballfields may begin the week of September 2, and the ballfield area will be closed during that time.
During construction, the tennis courts and basketball courts will remain open. Tennis courts can be accessed through the southern gate.
Thank you to the 71 respondents who selected their preferred paint colors for the Old Elm Shelter. The winning combination is the darker grey (D) on the bricks and the blue (A) on the panels.
The shelter is expected to be painted before the end of the year.
The roof on the Old Elm shelter has been replaced.
Take this survey to vote for your color preference before the survey closes on August 23.
The shelter roof is expected to be replaced on Wednesday, August 7.
The design process has been completed for the Old Elm Playground Renovation Project. Thank you to everyone who provided feedback through the survey, listening sessions and community meeting, to help shape the final design for the project. See the playground renderings here.
Construction is expected to begin in August and be completed by November.
Thank you to everyone who attended the Old Elm Park Playground meeting on Tuesday, November 14 and providing your preferences on the playground equipment options presented.
The feedback collected will be used to further refine the designs. Once designs are finalized, they will be posted to this page and the project will be bid out.
This past summer many of you participated in a survey to share your feedback on Old Elm Park. The Park District will host a community meeting on Tuesday, November 14, 2023, at Oak Terrace Elementary School to share the proposed playground design and two playground equipment options.
The meeting will start with a brief presentation providing an overview of the feedback collected this summer, the proposed layouts, and project timeline. After the presentation, participants will have the opportunity to review the equipment options and share their preferences. Feedback collected will be used to guide the final playground designs.
Meeting Details:
Date: Tuesday, November 14, 2023
Time: 6-7pm
Location: Oak Terrace Elementary School, Multi-Purpose Room
See the survey results from the preliminary playground planning survey here.
We will be at Old Elm Park on Friday, July 7 from 1-3pm to collect your feedback on the playground renovation.
The Park District of Highland Park would like to hear from you!
There will be several opportunities for the community to participate in the design process and the first is the Old Elm Playground Preliminary Planning survey. Follow this link to share your feedback in this brief survey.
The existing site is a collaboration between the City of Highland Park and the Park District of Highland Park. Consistent with the Intergovernmental Cooperation Act, the City owns the land, and the Park District manages all operations at the site through a 99-year Lease Agreement. The current Dome is owned by a third-party (Grantee) who is permitted to rent space for indoor recreation uses such as soccer, lacrosse, and other similar sports consistent with the terms of a Concession and Site Agreement (Dome Agreement). This Agreement was initiated in 2009 and has since been extended several times. The final term for the Agreement expired in April 2024.
In August 2023, the Park District released a request for proposals for a new long-term agreement that would meet the needs of the community. The Park District did not receive a proposal from the current Grantee but did receive three alternative proposals. In January 2024, after an extensive review process, the Park District enthusiastically accepted a proposal from Highland Park native Ronald Saslow for an indoor pickleball and padel facility. Mr. Saslow is contributing a major portion of the funding for the new facility, which will now be a year-round paddle facility.
The cost for both materials and installation of the air supported structure (dome) is roughly $1.4M. Construction of the court surface; the interior furniture, fixtures, and amenities; and adding utility services for sewer, water, and electric, will bring the total to roughly $4.2M. While a significant portion is covered by the generous donation from Mr. Saslow, the Parks Foundation of Highland Park is actively seeking donations and sponsorships to raise $600,000 to make the new indoor paddle facility a reality.
Over the past month, crews have made significant progress, including installing plumbing for the clubhouse structure and electric conduits throughout the dome area. Foundations for the padel courts have been dug and poured, while concrete pads for the mechanical units and generators have been completed, with the units now delivered and set in place. Asphalt work for the pickleball and padel courts has also been finalized.
In the coming month, crews will connect the mechanical units and generators to the electrical system. New sanitary sewer service, water lines, and piping for electric service will also be installed.
Check out a video update!
Over the past several months, the previous dome structure was demolished, and the site was prepared for new electrical service, water and sewer services, and construction of a new 50,000-square-foot dome.
The site is located on a landfill, which supports sustainable practices and requires strict adherence to Environmental Protection Agency guidelines. It is also adjacent to the Skokie River Drainage, which requires careful planning and permitting from several agencies, including the United States Army Core of Engineers, Lake County Strom Water Management, and the City of Highland Park.
• New water service will be provided across Route 41 to accommodate new fire hydrants, indoor fire suppression, new bathrooms and showers.
• Structural engineers have evaluated the foundation and improvements have been made to ensure the new facility will last for generations.
• The surface of the new facility has been graded to accommodate the necessary standards for pickleball and padel.
• The existing concrete has been cut to accommodate new plumbing, sewer, gas, and electricity to support the new mechanicals that will heat and cool the facility and low-voltage lines that support emergency exits, security cameras, and other audio/visual needs of the new facility.
Over the next month, asphalt and concrete work will be completed, preparing the site for construction of the new dome and interior structures. Before the dome is erected, the site will receive new electrical, plumbing, and sanitary sewer services. Due to unpredictable winter conditions, the dome will be inflated in Spring 2025 to ensure it can be completed safely. Soon after that, the interior structures that support patrons using the new Club Pickle and Padel will be constructed, and Pickleball and Padel Courts will be finalized.
We will continue to keep you updated on construction progress each month.
The final patchwork on the surfacing has been completed and the playground gates have been installed.
The playground is now open for play and features a new seating area!
Landscape restoration work within the tot lot has been completed.
Installation of the concrete entry walk and seating areas has been completed.
Installation of the new tot lot surfacing has been completed.
Installation of the new tot lot surfacing has begun.
Materials for the tot lot surfacing have been delivered. Installation of the new surfacing is expected to begin on Monday, September 16.
Replacement of the fencing around the elementary playground is nearing completion.
Replacement of the fencing around the tot lot is nearing completion.
The elementary playground will close for construction beginning in the afternoon on Wednesday, September 4.
Both playgrounds will be closed until the project is complete.
Concrete has been installed for the new seating area and entrance walk. Topsoil and turf restoration work has begun.
Demolition of the tot lot’s surfacing has been completed.
Construction on the Tot Lot is scheduled to begin Monday, August 19. Please note that the Tot Lot will be closed starting that day.
The elementary playground will remain open a few more weeks, until construction on the fence begins.
Thank you to everyone who provided playground equipment feedback at the open house and through the online survey.
The Park District heard from more than 50 people who selected their preferred playground equipment.
See the results here.
Thank you to those who attended the Community Open House on Tuesday, October 22.
If you couldn’t make it but would like to provide feedback on your preferred playground design, please take this survey before it closes on Nov 4, 2024.
Thank you to everyone who provided playground equipment feedback through the online survey and visits to the park. Through this effort, the Park District heard from more than 20 people at the park and 46 survey respondents.
Your feedback will be used to refine the playground design options. In September, the refined options will be shared, and the community will have the opportunity to select their favorite playground design.
See the survey results here.
The Planning and Projects team was at Rosewood Park on the following dates to share playground equipment options and collect feedback:
• Wednesday, July 24 from 9-11am
• Monday, July 29 from 3-5pm
• Tuesday, July 30 from 5-7pm
• Wednesday, Aug 7 from 9:30-10:30am
• Monday, Aug 12 from 4-5pm
Thank you to everyone who visited the park to share your feedback on the playground equipment! Your feedback will be used to refine the playground design options.
If you didn’t get a chance to stop by the park, or have more to say, please take the online survey before it closes on August 19.
We’ve heard some of you may not have received the postcard so we are adding two more park visits and extending the survey date! Please share with your neighbors!
Wednesday, Aug 7 from 9:30-10:30am
Monday, Aug 12 from 4-5pm
The roof replacement at Memorial Park has been completed.
The roof replacement at Memorial Park is expected to occur on Saturday, October 19.
The Golf Learning Center roof replacement has been completed.
The roof replacement on the Golf Learning Center is expected to begin the week of September 30.
The roof replacement at Memorial Park is expected to begin the week of September 23.
The roof replacement at Moraine Park has been completed.
The dugout roofs have been replaced at Sunset Woods.
The roof at the Sunset Woods Fieldhouse has been completed.
The roof on the Sunset Woods Fieldhouse is expected to be replaced on Friday, August 23, 2024.
The Moraine Park roof replacement is expected to begin August 9.
The roof at Old Elm has been replaced.
The roof at Old Elm Park is scheduled to be replaced August 7.
Thank you to everyone who provided playground equipment feedback at the open house and through the online survey.
The Park District heard from more than 30 people, and a playground design was selected.
See the results here.
On Thursday, September 26, the Park District hosted a Community Open House to share refined tot lot concept designs and collect feedback. Thank you to everyone who attended last night’s meeting!
If you couldn’t make it but would still like to provide feedback, please take the online survey before it closes on Friday, October 11.
Thank you to everyone who provided playground equipment feedback through the online survey and visits at the park. Through this effort, the Park District heard from more than 35 people at the park and 46 survey respondents.
Your feedback will be used to refine the playground design options. In September, two refined options will be shared, and the community will have the opportunity to select their favorite playground design.
See the survey results here.
The Planning and Projects team was at Larry Fink Park’s tot lot on the following dates to share playground equipment options and collect feedback
• Sat, June 15, from 10:30am-12:30pm
• Mon, June 24, from 3-5pm
• Tues, June 25, from 5-7pm
Thank you to everyone who visited the park to share your feedback on the playground equipment! Your feedback will be used to refine the playground design options.
If you didn’t get a chance to stop by the park, or have more to say, please take the online survey before it closes on July 19.
Thank you to everyone who provided playground equipment feedback at the open house and through the online survey.
The Park District heard from more than 80 people, and a playground design was selected.
See the results here.
On Tuesday, September 17, the Park District hosted a Community Open House to share refined playground concept designs and collect feedback. Thank you to everyone who attended last night’s meeting!
If you couldn’t make it but would still like to provide feedback, please take the online survey before it closes on Wednesday, September 25.
Thank you to everyone who provided playground equipment feedback through the online survey and visits to the park.
Through this effort, the Park District heard from more than 60 people at the park and 69 survey respondents. Your feedback will be used to refine the playground design options.
In September, the refined options will be shared, and the community will have the opportunity to select their favorite playground design.
See the survey results here.
The Planning and Projects team was at Lincoln Park on the following dates to share playground equipment options and collect feedback:
• Thursday, June 6, from 3:30-5:30pm
• Monday, June 10, from 9-11am
• Tuesday, June 18, from 5-7pm
Thank you to everyone who visited the park to share your feedback on the playground equipment! Your feedback will be used to refine the playground design options.
If you didn’t get a chance to stop by the park, or have more to say, please take the online survey before it closes on July 8.
The Park District of Highland Park was awarded $528,500 through the Open Space Lands Acquisition and Development (OSLAD) grant program administered by the Illinois Department of Natural Resources for improvements to Lincoln Park. The OSLAD grant is a state-funded program providing up to 50% of the project costs for public park and recreation projects.
Design will begin this summer and the community will have various opportunities to participate in the design process. Construction is expected to begin in summer of 2025.
The Park District of Highland Park submitted an Open Space Lands Acquisition and Development (OSLAD) grant for improvements to Lincoln Park.
Support from the OSLAD grant program would enable the Park District to adjust the layout of Lincoln Park to accommodate an elementary playground, increase basketball court space and address critical updates to Lincoln Park’s existing amenities. Updates include a new tot lot and improvements to the walking path, diamond fields and soccer field. The proposed concept for Lincoln Park was presented as Concept 2 in the August 15 Community Meeting.
Thank you to everyone who attended the August 15 community meeting. Your feedback will be used to guide the concept design to submit in the Park District’s grant application.
Click here to see the presentation.
The Park District of Highland Park will be hosting a community meeting on August 15, 2023 at 6pm at West Ridge Center (636 Ridge Road) to collect feedback for Lincoln Park.
The Park District of Highland Park heard the neighborhood’s interest in a new elementary playground due to the approved agreement to sell Lincoln School. Two design options have been developed that reconsider Lincoln Park with the addition of an elementary playground.
Feedback collected at this meeting will be used to assist in securing grant funding and to support adding an elementary playground at the park, which is currently unfunded.
If you cannot attend this meeting and would like to provide feedback, the presentation from the August 15th meeting will be posted to the project page on August 16th for those who are unable to make the meeting and would still like to provide feedback.
The Park District heard the neighborhood’s concerns over losing an elementary playground due to the sale of Lincoln School. As such, the Park District of Highland Park is going back to the drawing board to develop plans for Lincoln Park that consider the inclusion of an elementary play space. The comments and data collected through the survey will be integrated into the plans for the improved tot lot playground. There will be other opportunities to get involved in design as the Park District proceeds with planning. While the Park District will continue with the planning effort, the addition of an elementary playground is not currently budgeted in the Park District’s capital plan.
This change of direction will impact improvements scheduled for 2023. The tot lot, repaving of the path, and the patch/color of the basketball court planned for 2023 will be deferred to a future year and incorporated into the new plan.
The Park District will continue to follow the School District’s plans to coordinate efforts. Project updates will be posted to this web page.
Please direct questions and comments to [email protected].
The Park District of Highland Park is hosting listening sessions at Lincoln Park to collect feedback for the playground replacement.
Please stop by during one of the following times to share your thoughts!
• Friday, April 28 from 9:30-11am
• Wednesday, May 3 from 10-11:30am
• Tuesday, May 9 from 4:30-6pm
• Friday, May 12 from 2:30-4pm